Design of Pressure Networks


In principle, Designing Pressure Networks is done in EPANET. However, before you start Designing on EPANET, you may need to calculate the point demands Nodes we. This is done by evaluating population data to determine demand flows in the network.

To calculate the current demands on the network, follow the steps below:

  1. Make sure you have created at least one consumer sector
    This consumer sector will calculate based on the population projection, the demand data (for Pressure Networks) and infiltration (for Sewage Networks)
  2. During the network release, you can set the default consumption sector of the network
    In the network properties, define in Consumer Sectors / Consumption Sector
  3. If you forgot to define the consumption sector in the network, the pipes will not be associated with it. In this case, the association can be made after the end of the net launch. For that, select the pipes and in the Properties Tab look for Input and Output / Consumer Sectors. Note that it is possible to associate more than a consumption sector in the same pipe. Use this on pipes that are on sector boundaries and have mixed contribution
  4. After linking the Consumer Sectors to pressurized water pipes and/or sewer pipes, click the node Consumer Sectors and click Calculate All
    Note: This step is in case you want to view the calculated infiltration rates before calculating the networks. If you calculate the water and Sewage Networks, the program will check whether it is necessary recalculate the sectors before calculating the network